Cross Lanes Widening

Project Updates

SUMMARY OF CONSTRUCTION WORK:

12/192025 Project Update.

  

SUMMARY OF TEMPORARY TRAFFIC CONTROL: 

Changes expected beginning Week of 12/22/2025. 

No Striping of Roadway today 12/19/2025 due to weather. 

Roadway striping will be performed 12/22/2025-10:00 AM-8:00 PM.

EXPECT ADDITIONAL DELAYS THROUGH THE PROJECT ON 12/22/2025.

Opening of newly paved sections is scheduled 12/22/2025.

Cones will be used to delineate traffic lanes for a short period of time to allow for transitions to be completed and sections reopened.

Traveling public is asked to travel at Work Zone Speed Limit of 25 MPH while traveling through area.

Slow flaggers will be utilized during the Roadway Striping Day shift work.  These flaggers are to aid in the safety of traveling public.

What’s Changing?

Two Lanes heading from WV 62/622 intersection towards Kroger.

A Center Turn lane from WV 62/622 intersection towards Kroger.

One lane coming out of cross lanes.  From Kroger towards 64 E/W.

 


WVDOH Website, CLICK HERE:

WVDOH Cross Lanes project link with original traffic visualizations

Final Traffic Pattern Sketch: CLICK HERE

Final Traffic Sketch

Cross Lanes Widening

Latest News

Important project updates, announcements, and related local media stories.

10/13/2025 Update

Work on the project is progressing with minimal delays. Project is continuing to place curb and gutter, inlets, pipe and sidewalk as the primary items of focus. Work is being …

New Traffic Pattern 9/10/2025

Temporary Traffic Control Phase (2) will be in place beginning 9/10/2025 8:00 PM – WV 622 partial lane closure northbound beginning at I-64 West Bound Exit Ramp to Cadel Drive …

Project Update

July 28, 2025The Cross Lanes Widening Project is scheduled to resume construction beginning August 4, 2025.  Work will resume in the areas that are currently coned off from the Kroger …

April 02, 2025 Project Update

A few utilities remain throughout the project that still need to be relocated to allow contract work to proceed. Work on the project will be significantly minimized during the utility …

Update – Utilities

Various utilities throughout the project need to be relocated to allow contract work to proceed. Work on the project will be significantly minimized during the utility relocation efforts. The project …

New Phase of Construction

New Traffic Pattern!New Phase of Project has Begun.In the early A.M. hours of 6/14/2024 the Cross Lanes widening project made its second traffic switch for the phased construction.The current phase …

!!! Important Update !!!

Change in Start of New Traffic Pattern Reason For Change: The upcoming change in traffic pattern has been delayed, due to additional unforeseen work that requires additional time to perform.  …

Project Update – 05/13/2024

Notice of Traffic Pattern Change Location: WV 622 Big Tyler Road, Cross Lanes WV Scheduled Lane Shift: Beginning 5/15/2024, pending weather Description of Change: Due to the current construction along …