Weekly Look Ahead – 10/20/2025

Scheduled Work Week:  Monday – Friday  

Contractor: Triton Construction Inc

SUMMARY OF CONSTRUCTION WORK:

        • Work on the project is progressing with minimal delays.
        • Project is continuing to place curb and gutter, inlets, pipe and sidewalk as the primary items of focus.
        • Work is being performed in preparation for paving to begin on Monday Night 10/13/2025.
        • **Paving is scheduled from Cross Lanes Drive Intersection (WV 62) along Big Tyler Road (WV 622) to Kroger intersection.  Weather Dependent!**

        • Work is continuing at Gatewater Road and City National Bank intersection.    

Traffic will remain in the current state until the completion of phases 2, 10  and 13. The traveling public is asked to travel the Work Zone Speed Limit of 25 MPH while traveling through the area. Caution should be taken when exiting and entering driveways and area businesses. Traffic is asked to not block intersections and entrances when possible.

WVDOH Website, CLICK HERE:

WVDOH Cross Lanes project link with original traffic visualizations

Final Traffic Pattern Sketch: CLICK HERE

Final Traffic Sketch

Cross Lanes Widening

Latest News

Important project updates, announcements, and related local media stories.

10/13/2025 Update

Work on the project is progressing with minimal delays. Project is continuing to place curb and gutter, inlets, pipe and sidewalk as the primary items of focus. Work is being …

New Traffic Pattern 9/10/2025

Temporary Traffic Control Phase (2) will be in place beginning 9/10/2025 8:00 PM – WV 622 partial lane closure northbound beginning at I-64 West Bound Exit Ramp to Cadel Drive …

Project Update

July 28, 2025The Cross Lanes Widening Project is scheduled to resume construction beginning August 4, 2025.  Work will resume in the areas that are currently coned off from the Kroger …

April 02, 2025 Project Update

A few utilities remain throughout the project that still need to be relocated to allow contract work to proceed. Work on the project will be significantly minimized during the utility …

Update – Utilities

Various utilities throughout the project need to be relocated to allow contract work to proceed. Work on the project will be significantly minimized during the utility relocation efforts. The project …

New Phase of Construction

New Traffic Pattern!New Phase of Project has Begun.In the early A.M. hours of 6/14/2024 the Cross Lanes widening project made its second traffic switch for the phased construction.The current phase …

!!! Important Update !!!

Change in Start of New Traffic Pattern Reason For Change: The upcoming change in traffic pattern has been delayed, due to additional unforeseen work that requires additional time to perform.  …

Project Update – 05/13/2024

Notice of Traffic Pattern Change Location: WV 622 Big Tyler Road, Cross Lanes WV Scheduled Lane Shift: Beginning 5/15/2024, pending weather Description of Change: Due to the current construction along …