10/13/2025 Update
Work on the project is progressing with minimal delays. Project is continuing to place curb and gutter, inlets, pipe and sidewalk as the primary items of focus. Work is being …
The WV 622 – Cross Lanes Widening project will widen WV 622 from Goff Mountain Road to the intersection with WV 62 and on towards Andrew Jackson Middle School.
The project’s goals are to reduce traffic congestion, increase safety, and enhance stormwater management.
Weekly Look Ahead – 10/20/2025
Scheduled Work Week: Monday – Friday
Contractor: Triton Construction Inc
SUMMARY OF CONSTRUCTION WORK:
Traffic will remain in the current state until the completion of phases 2, 10 and 13. The traveling public is asked to travel the Work Zone Speed Limit of 25 MPH while traveling through the area. Caution should be taken when exiting and entering driveways and area businesses. Traffic is asked to not block intersections and entrances when possible.
WVDOH Website, CLICK HERE:
WVDOH Cross Lanes project link with original traffic visualizations

Phase 1: Gatewater Rd. STA 4000+00 – STA 4014+07 LT & RTConstruction: Sidewalk, Curb, Pavement, Drainage Improvements, Entrance to City Bank and County Lot. Phase 2: WV 622 Northbound STA 29+45 …
Phase 11: COMPLETED – Washington Street and Sun Valley Drive Construction: Drainage Improvements
Phase 12: COMPLETED – WV 622 Northbound STA 57+50 – STA 82+45 RTTraffic Control: Case A13 (MUTCD Typical Application 34)Construct: Retaining Walls 6 & 7, Sidewalk, Curb, Pavement, and Drainage …
Phase 14: WV 622 STA 57+50 – STA 81+45 CenterlineConstruct: Pavement, and Drainage Improvements.
The project began in mid-August 2023.
The projected completion date for the project is June 2025. Approximately 22 Months.
No, the design does not include any roundabouts.
Day and Night shifts will be utilized. The contractor will be required to work shifts that have the least amount of impact to the traveling public based of the phase of work being performed at the time.
During construction there will be multiple lane changes and switching of traffic patterns. Lane closures and shifts are necessary to perform all phases of construction. During construction north and south traffic will flow through a guided work zone with work zone construction signs, cones, barrels, and barricades to aid in directing flow of traffic. Some closures will be between the hours of 9:00 AM to 3:00 PM. The work zone speed limit will be 25 MPH.
Pedestrian traffic will be affected during certain stages of construction. During this time alternative routes may be required through the work zone with special attention to safety, However the contractor will be required to maintain access to all houses, schools, and businesses at all times.
The Contractor will notify businesses of updates to changing phases of traffic control in a specific location. The contractor will be required to maintain access at all times.
Please expect delays throughout the time frame of the project. Delays will be based on the current phase, location, and type of construction being performed daily. Delays are anticipated to be in early AM commute hours, Mid-Day hours, and PM commute hours.
Please do not block driveways and intersections.
Follow the project website: crosslaneswidening.com
Email: info@crosslaneswidening.com and ask to receive the weekly project update emails.
Some phases of work will be performed at night. This gives the perception the contractor is not working during the day. However, work is being performed at night in lieu of normal day time hours.
Currently, the project is under construction with some work beginning as early as August and September to move or relocate utilities. Construction on Sun Valley Drive and on WV 622 recently began. The project is proceeding on schedule.
These Apps can provide phone notifications of safety issues and traffic information in Kanawha County. Some include Public Notification System Opt-Ins.
Notifications in traffic pattern changes will be made via the digital message boards and the media.

Important project updates, announcements, and related local media stories.
Work on the project is progressing with minimal delays. Project is continuing to place curb and gutter, inlets, pipe and sidewalk as the primary items of focus. Work is being …
Temporary Traffic Control Phase (2) will be in place beginning 9/10/2025 8:00 PM – WV 622 partial lane closure northbound beginning at I-64 West Bound Exit Ramp to Cadel Drive …
July 28, 2025The Cross Lanes Widening Project is scheduled to resume construction beginning August 4, 2025. Work will resume in the areas that are currently coned off from the Kroger …
A few utilities remain throughout the project that still need to be relocated to allow contract work to proceed. Work on the project will be significantly minimized during the utility …
Various utilities throughout the project need to be relocated to allow contract work to proceed. Work on the project will be significantly minimized during the utility relocation efforts. The project …
New Traffic Pattern!New Phase of Project has Begun.In the early A.M. hours of 6/14/2024 the Cross Lanes widening project made its second traffic switch for the phased construction.The current phase …
On 6/5/2024 the project anticipates switching phases of traffic. The traffic affected will be along WV 62. The current pattern will be shifted from existing to opposite side. Traffic will …
Change in Start of New Traffic Pattern Reason For Change: The upcoming change in traffic pattern has been delayed, due to additional unforeseen work that requires additional time to perform. …
Notice of Traffic Pattern Change Location: WV 622 Big Tyler Road, Cross Lanes WV Scheduled Lane Shift: Beginning 5/15/2024, pending weather Description of Change: Due to the current construction along …