Cross Lanes Widening

Project Updates

SUMMARY OF CONSTRUCTION WORK:

04/06/2026 Project Update.

Construction Bulletin – Cross Lanes Project


Weekly Status:

The project remains on schedule. Contractor crews continued working day and night shifts throughout the week to maintain production and prepare the corridor for upcoming paving operations.


Work Completed This Week:

• Continued installation of drainage structures and pipe runs. Several structures required deep excavation, with average installation depths exceeding 10 feet, creating slower production and added safety considerations.
• Ongoing subgrade preparation and sidewalk bedding.
• Curb and gutter placement performed using hand‑form methods in areas inaccessible to slip‑form equipment.

Project Challenges:

• Numerous unknown utilities encountered throughout the winter months required redesigns and field adjustments.
• Adverse winter weather created continual delays and difficult working conditions.
Despite these issues, crews have maintained overall schedule progress.


Upcoming Work / Night Operations:

• Night shift work will continue for the foreseeable future to maintain traffic flow and accelerate production ahead of asphalt paving, which is targeted for mid‑May.
• Removal of the raised islands at the WV 62/622 intersection will occur during night operations to minimize traffic impacts.
• Continued drainage, grading, and base preparation activities.


General Notes:

• Expect ongoing nighttime lane closures and traffic shifts as work progresses.
• Additional updates will be issued as major milestones approach.


 

WVDOH Website, CLICK HERE:

WVDOH Cross Lanes project link with original traffic visualizations

Final Traffic Pattern Sketch: CLICK HERE

Final Traffic Sketch

Cross Lanes Widening

Latest News

Important project updates, announcements, and related local media stories.

10/13/2025 Update

Work on the project is progressing with minimal delays. Project is continuing to place curb and gutter, inlets, pipe and sidewalk as the primary items of focus. Work is being …

New Traffic Pattern 9/10/2025

Temporary Traffic Control Phase (2) will be in place beginning 9/10/2025 8:00 PM – WV 622 partial lane closure northbound beginning at I-64 West Bound Exit Ramp to Cadel Drive …

Project Update

July 28, 2025The Cross Lanes Widening Project is scheduled to resume construction beginning August 4, 2025.  Work will resume in the areas that are currently coned off from the Kroger …

April 02, 2025 Project Update

A few utilities remain throughout the project that still need to be relocated to allow contract work to proceed. Work on the project will be significantly minimized during the utility …

Update – Utilities

Various utilities throughout the project need to be relocated to allow contract work to proceed. Work on the project will be significantly minimized during the utility relocation efforts. The project …

New Phase of Construction

New Traffic Pattern!New Phase of Project has Begun.In the early A.M. hours of 6/14/2024 the Cross Lanes widening project made its second traffic switch for the phased construction.The current phase …

!!! Important Update !!!

Change in Start of New Traffic Pattern Reason For Change: The upcoming change in traffic pattern has been delayed, due to additional unforeseen work that requires additional time to perform.  …

Project Update – 05/13/2024

Notice of Traffic Pattern Change Location: WV 622 Big Tyler Road, Cross Lanes WV Scheduled Lane Shift: Beginning 5/15/2024, pending weather Description of Change: Due to the current construction along …