10/13/2025 Update
Work on the project is progressing with minimal delays. Project is continuing to place curb and gutter, inlets, pipe and sidewalk as the primary items of focus. Work is being …
Paving operations continue, with asphalt placement currently prioritized in critical areas where grade transitions and drop-offs are present. Crews are placing asphalt in staged lifts, including the initial base asphalt courses needed to build the roadway section to the required elevations and establish smoother transitions through the active widening limits. Additional base asphalt will be placed as needed to correct grade changes, improve tie-ins to existing pavement, and provide a stable surface for traffic during the current phase of construction. The anticipated traffic switch will take place in the early am hours of 7/20/2026. Attached to the email is a schematic that will provide a layout of the new traffic pattern. This switch will be the last major switch and begin the final phases of the project. During this switch, work will be completed for the widening portioning of the project. This phase is anticipated to last until the fall of 2026.
Beginning 7/16 and 7/17 lane shifts will be utilized to aid in establishing a new traffic pattern that will be utilized beginning in the AM hours of 7/20/2026.
Paving will be performed behind cones and at WV622 and 62 intersection. Flaggers will be used to aid in this process during night shift work.

WVDOH Website, CLICK HERE:
WVDOH Cross Lanes project link with original traffic visualizations
Important project updates, announcements, and related local media stories.