- Work on the project is progressing with minimal delays.
 - Project is continuing to place curb and gutter, inlets, pipe and sidewalk as the primary items of focus.
 - Work is being performed in preparation for paving to begin on Monday Night 10/13/2025.
 - Paving will be performed from Cross Lanes Drive Intersection (WV 62) along Big Tyler Road (WV 622) to Kroger intersection.
 - Work is continuing at Gatewater Road and City National Bank intersection.
 
SUMMARY OF TEMPORARY TRAFFIC CONTROL:
- No change in traffic pattern currently.
 - Traveling public is asked to travel at Work Zone Speed Limit of 25 MPH while traveling through area.
 - Flaggers will be utilized on Night Shift beginning 10/13/2025 for paving operations.
 - There is no designated turn lane or center lane on Big Tyler Road from intersection of WV 62 & WV 622. Traffic is asked to use caution and be prepared to stop during construction and to allow for turning traffic.
 - During this phase barriers were removed to allow for additional turning radiuses in and exiting area businesses.
 - Access to area residents being maintained during closures, this will be performed on as add needed basis to complete current phases.
 - Caution should be taken when exiting and entering driveways and area businesses.
 - Traffic is also asked to pay special attention to flaggers during night shift operations.
 - Traffic is asked to not block intersections and entrances when possible.
 
Sidewalks in current construction area have been removed and barricades in place to provide safety for pedestrians