Phase 1: Gatewater Rd. STA 4000+00 – STA 4014+07 LT & RT
Construction: Sidewalk, Curb, Pavement, Drainage Improvements, Entrance to City Bank and County Lot.
 
Phase 2: WV 622 Northbound STA 29+45 – STA 46+50 RT
Construction: Retaining Walls 1 & 2, Sidewalk, Curb, Pavement, and Drainage Improvements.

Phase 3: WV 622 Southbound STA 26+00 – 46+50 LT
Construction: Sidewalk, Curb, Pavement, and Drainage Improvements.
 
Phase 4: WV 622 Northbound STA 14+25 – STA 16+50 RT, STA 25+25 – STA 30+00 RT, & STA 26+45 – STA 29+05 Center
Construction: Curb, Drainage Improvements, and Install Guardrail.
 
Phase 5: WV 622 Southbound & WV 62 Eastbound STA 46+25 – STA 54+00 LT, STA 3000+25 – STA 3006+08 RT
Construction: Temporary Pavement, Retaining Wall 3, Sidewalk, Curb, Pavement, and Drainage Improvements.
 
Phase 6: COMPLETED – WV 622 Northbound & WV 62 Westbound STA 55+75 – STA 57+55 RT, STA 3500+00 – STA 3504+55 LT
Construction: Sidewalk, Curb, Pavement, and Drainage Improvements.
 
Phase 7: Island along WV 622 Northbound & WV 62 STA 55+25 – STA 56+00 RT
Construction: Curb, Install Controller Southeast Quadrant, Drainage Improvements, and Signal Poles Northeast, Southeast, and Northwest Quadrant.
 
Phase 8: Island along WV 622 & WV 62 Eastbound STA 53+50 – STA 54+35 LT
Construction: Sidewalk, Curb, and Pavement, Signal Pole Northwest Quadrant and Signal Heads all Quadrants.
 
Phase 9: WV 622 Northbound & WV 62 Eastbound STA 46+50 – STA 55+75 RT, STA 3500+00 – STA 3504+50 RT
Construction: Retaining Walls 4 & 5, Sidewalk, Curb, Pavement, and Drainage Improvements.
 
Phase 10: WV 622 Southbound & WV 62 Westbound STA 55+00 – STA 57+50 LT, STA 3001+00 – STA 3007+00 LT
Construction: Sidewalk, Curb, Pavement, and Drainage Improvements.