Notice of Traffic Pattern Change
Location: WV 622 Big Tyler Road, Cross Lanes WV
Scheduled Lane Shift: Beginning 5/15/2024, pending weather
Description of Change:
Due to the current construction along WV 622 Big Tyler Road in Cross lanes the current center turning lane has been closed for widening of WV 622 North, while shifting traffic traveling north along Big Tyler Road to the previous center turn lane. The next phase will shift WV 622 traffic heading south to previous turning lane while traffic heading north will be traveling along newly widened section that will have minimal construction being performed during night shift hours. The area affected by this lane shift will be from the intersection of Washington St W/Cross Lanes Drive to Dewitt Rd and Andrew Jackson Drive.
The duration of this phase of traffic shift is currently scheduled to be completed by Late August.
Message Boards along WV 622 and WV 62 have been changed to inform of upcoming changes beginning 5/15/2024, pending weather and the contractor’s preparedness.